Question: Immediate Most Activity Predecessors Optimistic Likely Pessimistic A -- 3 4 5 B -- 3 3 3 C A 2 3 4 D B 1
| Immediate | Most | |||
| Activity | Predecessors | Optimistic | Likely | Pessimistic |
| A | -- | 3 | 4 | 5 |
| B | -- | 3 | 3 | 3 |
| C | A | 2 | 3 | 4 |
| D | B | 1 | 3 | 5 |
| E | C | 4 | 4 | 4 |
| F | C | 2 | 2 | 2 |
| G | D,E | 4 | 5 | 6 |
| H | F,G | 3 | 4 | 5 |
| E(p) | V(p) | ||||
| 4 | 0.11 | V(p) | 0.89 | ||
| 3 | 0.00 | Std dev | 0.942809 | ||
| 3 | 0.11 | E(CP) | 20 | ||
| 3 | 0.44 | ||||
| 4 | 0.00 | ||||
| 2 | 0.00 | ||||
| 5 | 0.11 | ||||
| 4 | 0.11 | ||||
List all critical path activities
- Compute the expected completion time
- Calculate the probability of the following completion times:
- More than 22 weeks
- Less than 15 weeks
- Between 19 and 21 weeks.