Question: Immediate Most Activity Predecessors Optimistic Likely Pessimistic A -- 3 4 5 B -- 3 3 3 C A 2 3 4 D B 1

Immediate

Most

Activity

Predecessors

Optimistic

Likely

Pessimistic

A

--

3

4

5

B

--

3

3

3

C

A

2

3

4

D

B

1

3

5

E

C

4

4

4

F

C

2

2

2

G

D,E

4

5

6

H

F,G

3

4

5

E(p) V(p)
4 0.11 V(p) 0.89
3 0.00 Std dev 0.942809
3 0.11 E(CP) 20
3 0.44
4 0.00
2 0.00
5 0.11
4 0.11

List all critical path activities

  1. Compute the expected completion time
  2. Calculate the probability of the following completion times:
    1. More than 22 weeks
    2. Less than 15 weeks
    3. Between 19 and 21 weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!