Question: IMMEDIATE PREDECESSOR ACTIVITY B U D E F G H I A B B D C, E F G G H TIME (WEEKS) 11 12

IMMEDIATE PREDECESSOR ACTIVITY B U D E F G H I AIMMEDIATE PREDECESSOR ACTIVITY B U D E F G H I A

IMMEDIATE PREDECESSOR ACTIVITY B U D E F G H I A B B D C, E F G G H TIME (WEEKS) 11 12 23 3 10 6 5 10 9 a. What is the early start date for activity H? ES for H. 32 b. What is the late finish date for activity B? LF for B c. Determine the minimum number of weeks for completing the project. Minimum number of weeks d. How many weeks could activity F be delayed without delaying the project? Slack (in weeks) e. Assuming there are no delays (question part e is independent of question part d) or crashing, what is the critical path? Enter the activities in capital letters with hyphens (but no spaces) separating the activities. For example, A-C-G. Critical path (e.g., A-C-G)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!