Question: Immediate Predecessor Duration Budget (days) (SK) 0 -- Activity START A B D E F G co BN BE A,C,H 13 8 15 17 $50

Immediate Predecessor Duration Budget (days) (SK)

Immediate Predecessor Duration Budget (days) (SK) 0 -- Activity START A B D E F G co BN BE A,C,H 13 8 15 17 $50 $25 $40 $15 $35 $30 $20 $20 $28 $15 $20 15 6 BE E F,G F,G A,C,H F,G . I 11 12 K 20 Find: 1. Construct a baseline cost control curve (Time v. Budget) for the above project schedule. Assume daily costs are equally distributed throughout each activity's duration