Question: Immediate Predecessor(s) Activity B C D E F G H 1 J K Time (days) a m b 2 6 8 4 5 6 2

Immediate Predecessor(s) Activity B C D E F G H 1
Immediate Predecessor(s) Activity B C D E F G H 1 J K Time (days) a m b 2 6 8 4 5 6 2 3 4 6 7 8 2 4 6 1 2 3 7 9 14 11 13 5 7 9 15 17 19 5 9 13 12 BD . AE F G HI This exercise contains only part a a) Based on the activity time estimates, the expected times and variance for each of the activities are (Round your responses to two decimal places) Expected Time Variance Activity A B C D E F G H 1 J K