Question: Immediate Predecessor(s) Activity Time (days) a m b 4 5 8 3 4 5 1 2 3 - - 6 6 7 3 5 7

Immediate Predecessor(s) Activity Time (days) a m

Immediate Predecessor(s) Activity Time (days) a m b 4 5 8 3 4 5 1 2 3 - - 6 6 7 3 5 7 1 1 2 3 6 10 15 15 10 11 12 3 5 7 14 16 18 4 8 12 BD . AE F G C HI K This exercise contains only part a a) Based on the activity time estimates, the expected times and variance for each of the activities are: (Round your responses to two decimal places) Expected Time Activity A Variance OI JOOOOOOO! G Calculator