Question: Immediate Time ES EF LS LF Slack Activity Predecessor (days) A None 36 B A 42 C A 36 D B and C 22 E

Immediate

Time

ES

EF

LS

LF

Slack

Activity

Predecessor

(days)

A

None

36

B

A

42

C

A

36

D

B and C

22

E

D

12

  1. Create a network diagram with related attributes (activities and durations). You can draw the diagram manually or use any software. Next, copy and paste the diagram on your Word file.

  2. Identify all paths and their respective time, find the critical path, and calculate the project's total duration.

    Pathexample:A->....->....->..... ->E=...days.

  3. Calculate early start (ES), early finish (EF), late start (LS), late finish (LF), and total slack for each activity using forward pass and backward pass. For the last activity, assume LS = LF. Put those numbers (ES, EF, etc.) in the above table. You don't need to show me your step-by-step calculation for ES, etc. Just write the final result. (NOTES: Please use '0' to start the date).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!