Question: Implementing closedown includes the following major activities except: Shutting down resources and releasing to new uses. Creating a final report. E - mail the project

Implementing closedown includes the following major activities except:
Shutting down resources and releasing to new uses.
Creating a final report.
E-mail the project team that the project is complete.
Closing accounts and seeing all bills are paid.
Getting delivery acceptance from the customer.