Question: In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the
In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows:
2016 2017 2018
Costs incurred during the year $238,000$319,600$105,000
Estimated costs to complete357,000139,400-0-
Partial billings 260,000210,000380,000
Collections 240,000200,000410,000
20) Assuming the performance obligation is satisfied over time, what would be the gross profit in
2016?
A) $102,000
B) $260,000
C) $255,000
D) $425,000