Question: In 2 0 1 6 , Omega Construction began work on a contract with a price of $ 8 5 0 , 0 0 0

In 2016, Omega Construction began work on a contract with a price of $850,000 and estimated costs of $595,000. Data for each year of the contract are as follows:
\table[[,2016,2017,2018],[Costs incurred during the year,$238,000,$319,600,$105,000
 In 2016, Omega Construction began work on a contract with a