Question: In a batch machining operation on a conventional machine, setup time is 1 . 5 hours and batch size is 8 0 units. The cycle

In a batch machining operation on a conventional machine, setup time is 1.5 hours and batch size is 80 units. The cycle time consists of part handling time of 30 sec and processing time of 1.37 min. One part is produced each cycle. Tool changes must be performed every 10 parts and this takes 2.0 min. The reliability of this machine is characterized by mean time between failures of 37 hours and a mean time to repair of 55 min.
Determine
a) Average cycle time
b) Time to complete the batch
c) Average hourly production rate of the machine if availability is ignored.
d) Average hourly production rate of the machine if availability is taken into account.
e) Suppose that availability only applied during the actual run time of the machine and not the setup time. Determine the average hourly production rate of the machine

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!