Question: In a batch machining operation on a conventional machine, setup time is 1 . 5 hours and batch size is 8 0 units. The cycle
In a batch machining operation on a conventional machine, setup time is hours and batch size is units. The cycle time consists of part handling time of sec and processing time of min. One part is produced each cycle. Tool changes must be performed every parts and this takes min. The reliability of this machine is characterized by mean time between failures of hours and a mean time to repair of min.
Determine
a Average cycle time
b Time to complete the batch
c Average hourly production rate of the machine if availability is ignored.
d Average hourly production rate of the machine if availability is taken into account.
e Suppose that availability only applied during the actual run time of the machine and not the setup time. Determine the average hourly production rate of the machine
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock