Question: In a binary integer programming problem, 1 corresponds to a yes decision and 0 to a no decision. If project S can be undertaken only
In a binary integer programming problem, 1 corresponds to a yes decision and 0 to a no decision. If project S can be undertaken only if project T is also undertaken, then the following constraint needs to be added to the formulation:
| S + T = 1 | ||
| T S | ||
| S + T 1 | ||
| S T |