Question: In a binary integer programming problem, there are three projects (X1, X2, and X3) the constraint if project 1 cannot be selected if both projects

In a binary integer programming problem, there are three projects (X1, X2, and X3) the constraint if project 1 cannot be selected if both projects 2 and 3 selected would be written _____.

Group of answer choices

X1 + X2 + X3 1

X1 X2 X3 1

X1 + X2 + X3 0

None of the choices is correct.

X1 + X2 + X3 2