Question: In a binary integer programming problem, there are three projects (X1, X2, and X3) the constraint if project 1 cannot be selected if both projects

In a binary integer programming problem, there are three projects (X1, X2, and X3) the constraint if project 1 cannot be selected if both projects 2 and 3 selected would be written _____.

a X1 + X2 + X3 2

b X1 X2 X3 1

c X1 + X2 + X3 1

d X1 + X2 + X3 0

e None of the choices is correct.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!