Question: In a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a
In a complex and critical project, a sponsor asks the risk manager to determine where the project's concentration of risks is greatest by performing a quantitative risk analysis. There are no organizational process assets (OPAs)s about the risk categories. Which tool could the risk manager use to discover the project risk categories? Work breakdown structure (WBS) Mind mapping Monte Carlo simulation Affinity diagram
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
