Question: In a construction project, a stone cladding activity is planned to be carried out. The stone quantity is estimated to be around 2 1 5

In a construction project, a stone cladding activity is planned to be carried out. The stone quantity is estimated to be around 2152m2. The foreseen productivity for a stone mason and a helper is around 17m2? day (8 hours per day). The contracting company pays the stone mason a rate of 21$? hour, while it pays the helper a rate of 12$? hour. It also pays each one of them 6 $/day against transportation cost, and each one of them is covered by a health insurance which costs the company around 91 $/week. Both labors will work 8 hours per day, 5 days a week.
Based on the given information, answer the given questions below:
Find the direct labor unit cost?
 In a construction project, a stone cladding activity is planned to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To find the direct labor unit cost follow these steps Step 1 Calculate Daily Labor Cost for Each Wor... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!