Question: In a construction project, a stone cladding activity is planned to be carried out. The stone quantity is estimated to be around 2 1 5
In a construction project, a stone cladding activity is planned to be carried out. The stone quantity is estimated to be around m The foreseen productivity for a stone mason and a helper is around mday hours per day The contracting company pays the stone mason a rate of $hour while it pays the helper a rate of $hour It also pays each one of them $day against transportation cost, and each one of them is covered by a health insurance which costs the company around $week Both labors will work hours per day, days a week.
Based on the given information, answer the given questions below:
Find the direct labor unit cost?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
