Question: In a construction project where the contractor has a specific number of days to do the work, the time begins (and the contract is encumbered)
In a construction project where the contractor has a specific number of days to do the work, the time begins (and the contract is "encumbered") when the owner:
A: Can beneficially occupy the project
B: opens bids
C: issues a Notice to Proceed
D: awards the contract