Question: In a construction project where the contractor has a specific number of days to do the work, the time begins (and the contract is encumbered)

In a construction project where the contractor has a specific number of days to do the work, the time begins (and the contract is "encumbered") when the owner:

A: Can beneficially occupy the project

B: opens bids

C: issues a Notice to Proceed

D: awards the contract