Question: In a cycle batch processing, which of the following components is NOT directly required to compute the optimal/economical size of a batch order? Unit Cost:
In a "cycle batch" processing, which of the following components is NOT directly required to compute the optimal/economical size of a batch order?
Unit Cost: C
Holding Cost: H
Fixed Cost: S
Throughput: R