Question: In a long - running high - production operation, the starting work material cost = $ 0 . 6 5 p c , and

"In a long-running high-production operation, the starting work material cost =$0.65pc, and cycle time =1.28min. Equipment cost rate =$44.00hr, and labor cost rate =$28.00hr. Both rates include overhead costs. Tooling cost =$0.05? pc. Availability of the production machine =95%, and the scrap rate =4%. Determine the finished part cost in $pc."
 "In a long-running high-production operation, the starting work material cost =$0.65pc,