Question: Question 6 ( 1 5 points ) DDT precision manufacturing runs an automated production operation, the starting work part cost = 5 0 cents each,

Question 6(15 points)
DDT precision manufacturing runs an automated production operation, the starting work part cost =50 cents
each, and the cycle time is captured in the table below.
Equipment cost rate =R30.00hr, and labor cost rate =R25.00hr. Both
rates include overhead costs. Tooling cost = R0.08/pc. Availability of the production
machine =96%, and the scrap rate =3%.
Determine the following
Production rate and
Finished part cost.