Question: In a manufacturing process, a molded part spends 8 hours in inventory before being placed in a deburring machine, where the part is processed for
In a manufacturing process, a molded part spends 8 hours in inventory before being placed in a deburring machine, where the part is processed for 5 minutes. After deburring, the part spends 7 hours in inventory waiting for its turn on the polishing machine. The part then spends 6 minutes in polishing before waiting 8 hours in line to be painted. The part goes through a painting process that takes 9 minutes, then spends 22 hours in inventory before being shipped to the customer.
What is the percentage of value-added time for the part?