Question: In a medical test processing lab, samples need to be prepared before being entered into the testing machines. At this preparation stage the cycle time
In a medical test processing lab, samples need to be prepared before being entered into the testing machines. At this preparation stage the cycle time is 90 minutes per 100 samples by 1 worker.
If 3 workers are assigned to this preparation stage, and each worker works for one 8 hrs shift, what is the capacity of this stage?
PLEASE SHOW A STEP BY STEP SOLUTION SO THAT I WILL UNDERSTAND HOW TO WORK OUT THESE TYPES OF PROBLEMS. COULD YOU RECOMMEND A BOOK TO HELP ME ALSO? THANK YOU VERY MUCH!
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts