Question: In a network disgram, Activity 1 2 cant start until Activities 1 0 and 1 1 are both finished. What type of relationship does this

In a network disgram, Activity 12 cant start until Activities 10 and 11 are both finished. What type of relationship does this suggest?
a a start-to-start relationship
b a start-to-finish relationship
c.q, a finish-to-finish relationship
6q, a finish-vo-start relationship