Question: In a PERT problem our project has an expected duration of 100 days and a standard deviation of completion of 2 days. When will we

In a PERT problem our project has an expected

In a PERT problem our project has an expected duration of 100 days and a standard deviation of completion of 2 days. When will we be finished with 97.50% probability? Again, the normal curve data that we have been using comes from the chart on page 866 (Table A in Appendix B). 97.5 days 100.2 days 101.7 days 103.9 days 110.8 days