Question: need full answer please Question 1 a) The Customer on a project tells the project manager they have run out of money to pay for

need full answer please need full answer please Question 1 a) The
Question 1 a) The Customer on a project tells the project manager they have run out of money to pay for the project. Explain FIVE (5) actions should the project manager do. (10 marks) b) You are evaluating two projects. Project A has an expected duration of 90 days with a standard deviation of 10 days and project B has an expected duration of 100 days with a standard deviation of 4 days. Choose with justifications which project is more risk. (6 marks) c) This project is chartered to determine new ways to extend the product life of one of the company's medium- producing products. The project manager comes from the engineering department and the team comes from the product management and marketing departments. The project scope statement and project planning are completed when a stakeholder notifies the team that there is better way to complete one of the work packages. The stakeholder supplies a technical review letter from his department proving that the new way to complete the work package will actully be faster than the old way. The project manager has had similar experiences with this department on others projects and was expecting this to happen on this project. Predict THREE (3) best prevention action the project manager should do. (9 marks) [Total: 25 Marks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!