Question: In a project activities are given as acrows from vertices A . B . C . D and E in a directed graph and the

In a project activities are given as acrows from vertices A. B. C.D and E in a directed graph and the weeks taken for each activity are given as integers along the arrows (Mealy method). We need to start the project from A and end in E. The-Graph is given in the attached document and below.
CPM MF-1docx =
Identify all the paths (inciuding the weeks) and the critical path among all the paths and time taken in weeks for Critical Path Completion.
 In a project activities are given as acrows from vertices A.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer