Question: In a project, activity A, B, and C are the successors of activity D. The LSTs of activities A, B, and C are week 10,
In a project, activity A, B, and C are the successors of activity D. The LSTs of activities A, B, and C are week 10, week 12, and week 7, what are the LST ____ and LFT ____ for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input LST in the first blank and LFT in the second blank.)