Question: In a project, activity A, B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A, B, and C
In a project, activity A, B, and C are the predecessors (or prerequisites) of activity D. The EFTs of activities A, B, and C are week 5, week 7, and week 4, what are the EST for activity D? Assume that activity D has 6-week task duration. Round your answer to the nearest integer. (Input EST in the first blank and EFT in the second blank.) and EFT
Step by Step Solution
3.29 Rating (155 Votes )
There are 3 Steps involved in it
I For calculating EST Early Start time and EFT Early Finish time we must look at forward ... View full answer