Question: In a project activity network, activity F has three immediate predecessors: B, C, and E. The earliest completion times for B,C, and E are 7,17

In a project activity network, activity F has
In a project activity network, activity F has three immediate predecessors: B, C, and E. The earliest completion times for B,C, and E are 7,17 , and 8 days. What is the earliest start time for F