Question: In a project activity network, activity F has three immediate predecessors - B, C, and E. The earliest completion times for B is day 5,

In a project activity network, activity F has three immediate predecessors - B, C, and E. The earliest completion times for B is day 5, for C is day 18, and that for E is day 11. What is the earliest start time for F?

(note: according to our convention, if preceding activities finish on day 2, we can start the following activity on day 2 - there is no need to add one and say that the following activity can start only on day 3)