Question: In a project, extreme deviation ranges are estimated at plus or minus 3 sigmas. Which of the following has the lowest risk? Select the correct
In a project, extreme deviation ranges are estimated at plus or minus 3 sigmas. Which of the following has the lowest risk? Select the correct answer Mean of 29 days Optimistic: 26 days, Most Likely: 30 days, Pessimistic: 33 days 22 to 30 days 5 to 30 days