Question: In a project management workshop, an instructor is explaining the concept of critical paths in network diagrams to a group of new project managers. The
In a project management workshop, an instructor is explaining the concept of critical paths in network diagrams to a group of new project managers. The instructor asserts that regardless of the complexity or size of the project, every project network will have at least one path that is critical to the projects completion time. The new project managers are required to recognize the validity of this assertion. Is the instructor's statement accurate?
True or False: Every network has at least one critical path.
Group of answer choices
True
False
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock