Question: In a Project Network, an activity that has more than one activity immediately preceding it ( and thus more than on dependency arrow flowing into

In a Project Network, an activity that has more than one activity immediately preceding it (and thus more than on dependency arrow flowing into it) is called:
Group of answer choices
a merge activity
a burst activity
a dummy activity
a non-path activity
a termination activity