Question: In a project network diagram, if an activity has a slack time of zero, it means: a . The activity is on the critical path
In a project network diagram, if an activity has a slack time of zero, it means:
a The activity is on the critical path
b The activity is not important for project completion
c The activity can be delayed without affecting project completion
d The activity has the longest duration
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock