Question: In a project network, if the earliest an event can take place is week 3 8 the most likely time it will take place is
In a project network, if the earliest an event can take place is week the most likely time it will take place is week and the latest it can take place without delaying project completion is week at is the event slack time?
Group of answer choices
weeks
weeks
weeks
weeks