Question: In a project network, if the earliest an event can take place is week 36 the most likely time it will take place is week

In a project network, if the earliest an event can take place is week 36 the most likely time it will take place is week 42and the latest it can take place without delaying project completion is week 44, at is the event slack time? 0 8 weeks 0 2 weeks 4 weeks 6 wecks