Question: In a project network, if the earliest an event can take place is week 36 the most likely time it will take place is week

In a project network, if the earliest an event

In a project network, if the earliest an event can take place is week 36 the most likely time it will take place is week 42and the latest it can take place without delaying project completion is week 44, at is the event slack time? 0 8 weeks 0 2 weeks 4 weeks 6 wecks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!