Question: In a Work Breakdown Structure ( WBS ) the costs attached to subdeliverables Select one: OA should be subtracted directly from deliverable costs. B .

In a Work Breakdown Structure (WBS) the costs attached to subdeliverables
Select one:
OA should be subtracted directly from deliverable costs.
B. are called phantom costs.
C. are the summary of the work packages that support it.
D. are not recoverable unless explicitly stated in the WBS.
OE are bogus costs.
 In a Work Breakdown Structure (WBS) the costs attached to subdeliverables