Question: In an activity-on-node network diagram created by your team, activity F is preceded by activities D and E, and succeeded by activity G. Activity F
In an activity-on-node network diagram created by your team, activity F is preceded by activities D and E, and succeeded by activity G. Activity F is: Question 3 options: 1) A burst node. 2) A merge node. 3) Already late. 4) Highly uncertain duration