Question: In an adaptive or change - driven project life cycle: a . early results lead into planning later work. b . the product or deliverable

In an adaptive or change - driven project life cycle:
a.
early results lead into planning later work.
b.
the product or deliverable is well understood.
c.
planning precedes all executing.
d.
the waterfall approach is commonly used.