Question: Which response is correct in an adaptive or change - driven project life cycle? Question 3 3 Select one: a . the product is well
Which response is correct in an adaptive or change driven project life cycle?
Question Select one:
a
the product is well understood.
b
all planning precedes all executing.
c
early results lead into planning later work.
d
the waterfall approach is commonly used.