Question: In calculating OEE ( Overall Equipment Effectiveness ) what will be the availability factor, if in 8 hours shift the machine needed adjustment and 1
In calculating OEE Overall Equipment Effectiveness what will be the availability factor, if in hours shift the machine needed adjustment and hour was lost in that. pt
b
c Cannot determine
d