Question: In cell D 3 , enter your full name. Problem: In cells A 1 7 :G 2 4 , there is a table of activities
In cell D enter your full name.
Problem:
In cells A:G there is a table of activities associated with a project at Michael Williams software firm in Maine. This table states the Immediate predecessors and their durations. In cells A:AA there is an incomplete critical path diagram that you will need to fill out.
In the
Note: the Early Start and Early Finish of each activity.
Note: the cells that should contain inputted values are G I G I L N L N L N Q S Q and S
In the
Note: the cells that shou input the backwards pass Late Finish and Late Start of each activity.
Note: the key shate contain inputted values are G I G I L N L N L N Q S Q and S
In cell H key on where the LF and LS are within each diagram can be found in cells W:AA
In cell H input how many weeks the project should take based on your analysis you did above.
In cells H J and L input the activities in order on the critical path.
tableActivitytableImmediatePredecessorstableDurationweeksABCADAEA BFC EGD
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock