Question: Instructions: In cell D 3 , enter your full name. Problem: In cells A 1 7 :G 2 4 , there is a table of

Instructions:
In cell D3, enter your full name.
Problem:
In cells A17:G24, there is a table of activities associated with a project at Future software firm in Tuscaloosa. This table states the immediate predi
their durations. In cells A25:AA37, there is an incomplete critical path diagram that you will need to fill out.
In the eard input the forward pass (Early Start and Early Finish) of each activity.
Note: the cells that should contain inputted values are G28,128, G32,132, L25, N25, L29, N29, L34, N34, Q27, S27, Q34, and S34.
Note: the key on where the ES and EF are within each diagram can be found in cells W17:AA21
In the
input the backwards pass (Late Finish and Late Start) of each activity.
Note: the cells that should contain inputted values are G30, I30, G34, I34, L27, N27, L31, N31, L36, N36, Q29, S29, Q36, and S36.
Note: the key on where the LF and LS are within each diagram can be found in cells W17:AA21
In cell H4O, input how many weeks the project should take based on your analysis you did above.
In cells H42, J42, and L42, input the activities (in order) on the critical path.
Instructions:
In cell D3, enter your full name.
Problem:
In cells A17:G24, there is a table of activities associated with a project at Future software firm in Tuscaloosa. This table states the Immediate predecessors and their durations. In cells A25:AA37, there is an incomplete critical path diagram that you will need to fill out.
In the input the forward pass (Early Start and Early Finish) of each activity.
Note: the cells that should contain inputted values are G28,128, G32,132, L25, N25, L29, N29, L34, N34, Q27, S27, Q34, and S34.
Note: the key on where the ES and EF are within each diagram can be found in cells W17:AA21
In the input the backwards pass (Late Finish and Late Start) of each activity.
Note: the cells that should contain inputted values are G30, I30, G34, I34, L27, N27, L31, N31, L36, N36, Q29, S29, Q36, and S36.
Note: the key on where the LF and LS are within each diagram can be found in cells W17:AA21
In cell H40, input how many weeks the project should take based on your analysis you did above.
In cells H42. J42, and L42, input the activities (in order) on the critical path.
\table[[Activity,\table[[Immediate],[Predecessors]],\table[[Duration],[(weeks)]]],[A,-,8],[B,-,4],[C,A,3],[D,A, B,12],[E,A, B,4],[F,C, E,10]]
Michael Williams' project will take: weeks.
The critical path for the project is:
 Instructions: In cell D3, enter your full name. Problem: In cells

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!