Question: In CPM scheduling, FS, FF, and SS stand for: Group of answer choices Final Slip, First Finish, Start Slip First Start, Final Finish, Schedule Start

In CPM scheduling, FS, FF, and SS stand for: Group of answer choices Final Slip, First Finish, Start Slip First Start, Final Finish, Schedule Start Finish-to-Start, Finish-to-Finish, Start-To-Start Float Slip, Final Float, Schedule Slack