Question: In Critical Path (CPM) scheduling, FS, FF, and SS stand for: Group of answer choices a. Final Slip, First Finish, Start Slip b. First Start,
In Critical Path (CPM) scheduling, FS, FF, and SS stand for: Group of answer choices a. Final Slip, First Finish, Start Slip b. First Start, Final Finish, Schedule Start c. Finish-to-Start, Finish-to-Finish, Start-To-Start d. Float Slip, Final Float, Schedule Slack
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts