Question: In crashing a project, a manager will generally focus on activities whicha. are not on the critical path b . are the least costly to
In "crashing" a project, a manager will generally focus on activities whicha.
are not on the critical path
b
are the least costly to crash
c
are costly to crash and are on the critical path
d
are on the critical path and are the least costly to crash
e
none of the choices are correct.