Question: In creating a PERT chart, the rule that states that before an activity can start, all its immediate predecessors must be finished, is the: Group
In creating a PERT chart, the rule that states that before an activity can start, all its immediate predecessors must be finished, is the:
Group of answer choices (select all that apply)
1. Earliest Start Time Rule
2. Latest Finish Time Rule
3. Earliest Finish Time Rule
4. Latest Start Time Rule
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock