Question: In creating a PERT chart, the rule that states that before an activity can start, all its immediate predecessors must be finished, is the: Group

In creating a PERT chart, the rule that states that before an activity can start, all its immediate predecessors must be finished, is the:

Group of answer choices (select all that apply)

1. Earliest Start Time Rule

2. Latest Finish Time Rule

3. Earliest Finish Time Rule

4. Latest Start Time Rule