Question: In December 2014, Custom Mfg. established its predetermined overhead rate for jobs produced during year 2015 by using the following cost predictions: overhead costs, $750,000,
In December 2014, Custom Mfg. established its predetermined overhead rate for jobs produced during year 2015 by using the following cost predictions: overhead costs, $750,000, and direct labor costs, $625,000. At year-end 2015, the companys records show that actual overhead costs for the year are $830,000. Actual direct labor cost had been assigned to jobs as follows.
Jobs completed and sold $ 513,750
Jobs in finished goods inventory 102,750
Jobs in work in process inventory 68,500
Total actual direct labor cost $ 685,000
Enter the overhead costs incurred and the amounts applied during the year using the predetermined overhead rate and determine whether overhead is overapplied or underapplied.
| Factory Overhead | |||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts