Question: In earned value analysis ( EVA ) , we found: SV = - $ 7 , 8 0 0 at certain point. If the project
In earned value analysis EVA we found: SV $ at certain point. If the project has a total budget $ and total duration of days. The project is:
On schedule
Ahead of schedule by day
Ahead of schedule by days
Behind schedule by day
Behind schedule by days