Question: In earned value analysis, the 0 - 1 0 0 percent rule allows 0 percent credit when work begins and 1 0 0 percent credit
In earned value analysis, the percent rule allows
percent credit when work begins and percent credit at completion of the activity
percent credit before starting work and percent credit after the completion
percent credit when work begins and percent credit when the project is complete
percent credit at completion of the activity and percent credit at formal acceptance during scope verification